Replacing Heating in an Occupied School During the Summer Break
School heating replacement over the summer break
A practical guide to replacing school heating while clubs, staff and site teams still need access.

Start with the school calendar and a floor plan. Mark the rooms needed for holiday clubs, results day and staff access. Use the remaining rooms to plan the first phase of work.
- Before term endsSurvey occupied rooms and confirm the brief.
- Before contractors arriveAgree closures, access and outages.
- During the worksRelease and return rooms by wing.
- Before pupils returnTest each zone with the caretaker.
What should you survey before term ends?
- Walk the school with the caretaker. Record rooms that warm slowly, share a thermostat or host evening bookings.
- Brief the designer. Supply floor plans, ceiling heights, glazing details and fuel records for a room-by-room heating assessment.
- Check shared services. Ask the designer to assess electrical capacity and identify any hot-water services affected by a boiler shutdown.
Which rooms can you release together?
Trace the contractor’s delivery route and the routes staff and holiday clubs still need. Four classrooms might be available together, but their corridor could be the only route to the club toilets.
On the phase plan, record the room numbers, access route, agreed outages, hand-back date and person responsible. Allow time for testing, cleaning and furniture before the next wing closes.
Match the heating specification to the room
- Controls. Specify separate schedules where classrooms and evening lettings use different hours.
- Ceiling layout. Show heating areas alongside lighting, detectors and access panels on one coordinated drawing.
- Comparable quotes. Ask bidders to include reinstatement, commissioning and training, and to state the tariff and occupied hours behind each cost estimate.
Explore heating for education buildings · View education projects
What needs checking before pupils return?

- Ask the installer to demonstrate that each room controller operates the intended zone. Record the result against the room number on the plan.
- Have the caretaker set a normal school week, an evening booking and a holiday override, then restore the agreed timetable.
- Collect commissioning records, as-installed drawings, operating instructions and the contact for faults before signing off the phase.
- Book a follow-up during the first cold spell. A summer handover can confirm the controls work, but winter conditions are needed to assess morning warm-up and comfort in use.
School heating replacement FAQs
Can a holiday club stay open during heating works?
It may be possible if the school and contractor agree how the club will retain access, toilets and required services throughout each phase. Check the route at delivery times as well as during club hours.
Does replacing classroom heating also affect hot water?
It can if the same plant supplies both. Before booking an isolation, ask the designer to trace the services to kitchens, toilets and occupied rooms and agree how they will operate during the outage.
How can estates teams compare running-cost estimates?
Give each bidder the same room schedule and tariff. Ask for estimated annual electricity or fuel use alongside the annual cost so you can see how evening lettings and holiday opening affect the comparison.
What can the caretaker test before September?
Check each thermostat against its room, programme a normal school week and try an evening override. Arrange a cold-weather follow-up to assess morning warm-up under occupied conditions.
Planning summer heating works at your school?
Send your floor plan, term dates and a list of rooms that must stay open. Identify any ceilings already scheduled for refurbishment so Energy Carbon can discuss suitable heating layouts with your estates team.
Discuss your school heating project